Construction at Movala is on schedule, with progress happening every day. See below some exciting new developments and join us on-site by watching the video! 

  • The south tower crane started operating in early September
  • The second out of eight raft pours was completed in late August, where over 1500 cubic meters of concrete was poured. The third raft pour has just started. 
  • 80 out of over 700 piles remain to be completed 
  • Forming and reinforcing vertical elements (walls & columns) has begun in the southwest corner