Construction at Movala is on schedule, with progress happening every day. See below some exciting new developments and join us on-site by watching the video!
The south tower crane started operating in early September
The second out of eight raft pours was completed in late August, where over 1500 cubic meters of concrete was poured. The third raft pour has just started.
80 out of over 700 piles remain to be completed
Forming and reinforcing vertical elements (walls & columns) has begun in the southwest corner